Can someone give me a bit of guidance for the configuration for the battery cells orientation I found a similar one in the forum but without the batteries it’s 6s4p but this is only way I can squeeze into the hatch this is layout of a Chinese pack I purchased for testing which needed copper sandwich for the load and welds were poor the cells below are ampace jp40 cells which are 70amp continuous id like to arrange in best way to use widest busbar possible thanks David
I would build it like that
Make sure to reinforce (double or triple) the strips in the 2 marked areas
Or just make it a 8S3P pack, easier to connect
And use Battery Pack Spacer Generator to generate the needed “metal” outlines and spacers ![]()
Nice tool, how can I force it to follow the 3x8 grid OP requested? Or will it only work for the 8S3P approach then?
My dad is working on it.
1 Like
That would be a thought but I can only run 12 s on esc so would be a fair drop in the running time considerably thanks for getting back so quickly I’ll cut my copper sheet to this design and get on it many thanks David
I’m running two in serial I forgot to mention it on post